Transco - Blow Down Notification 

 

Notice

The schedule below is for the process to taking the existing "B" line out of service for the Skillman loop construction.  The blow down and recompression will take place at the Belle Mead valve site in Montgomery township (across from the quarry) beginning tomorrow.

Landowners at and near Coventry Farms have been notified that there will be noise and may be a slight odor of gas when the line is cut at Coventry Farms if there is any residual gas in the line after the pressure is gone. 

(Blow Down and Recompression) at Montgomery 28 Valve Site and Coventry Farm Site.

SCHEDULE
Thursday 4/30              7am to 7pm - ODOR
Friday 5/1 -                   7am  to  Saturday 5/2 - 11pm   (NOISE & ODOR)
Sunday 5/3                    7am to 7pm - ODOR
Monday 5/4                   6am to 12am - ODOR
Tuesday 5/5                  6am to 12am - ODOR

Williams - Transco
24 Hour Office Number – (610) 419-9145